A2106/26
Checking status...
OBSCrane Operations

Heathrow crane operations are restricted to runway-closure periods and prohibited in LVP.

2026-06-08 21:30 - 2026-09-08 03:30
Duration:aggregated 23 days

Period of Applicability

2026-06-08 21:30 - 2026-09-08 03:30

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

A crane will operate in the Heathrow area within the stated coordinates up to 136 ft AGL/216 ft AMSL, only between 2130 and 0330, only when runway 09L/27R is closed, and no crane operation is permitted in low visibility procedures.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A2106/26 NOTAMN
Q) EGTT/QOBCE/IV/M  /AE/000/003/5128N00027W001
A) EGLL B) 2606082130 C) 2609080330
D) 2130-0330
E) LIT CRANE OPR BTN 512828N 0002706W - 512828N 0002703W -
512827N 0002702W - 512827N 0002705W - 512828N 0002706W (HEATHROW).
MAX HGT 136FT AGL, 216FT AMSL. CRANE WILL ONLY OPR WHEN RWY 09L/27R
IS CLSD. NO CRANE OPR IN LVP. CRANE REF 20260602162