A1101/26
Checking status...
OBSConstruction Activity

Construction equipment is positioned before runway 19L and right of its extended centerline.

2026-10-05 05:00 - 2026-10-23 16:00
Duration:19 days

Period of Applicability

2026-10-05 05:00 - 2026-10-23 16:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Work in progress with construction equipment located 400 m before the threshold of runway 19L and 150 m right of the extended runway centerline. The equipment has a maximum height of 33 ft AGL and an elevation of 122 ft AMSL.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A1101/26 NOTAMN
Q) ESAA/QFAHW/IV/BO /A /000/999/5939N01755E005
A) ESSA B) 2610050500 C) 2610231600
E) WIP 400M BEFORE THR RWY 19L AND 150M RIGHT OF EXTENDED RCL.
CONSTRUCTION EQPT MAX HGT 33FT AGL ELEV 122FT AMSL.