10/019
Checking status...
Airport maintenance

Main ramp work in progress barricaded area.

2024-10-29 19:07 - 2024-11-29 22:00

Period of Applicability

2024-10-29 19:07 - 2024-11-29 22:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, cancel anytime

Interpretation

Excavation adjacent to the southeastern side of the main ramp is barricaded, impacting operations from October 29, 2024, at 19:07 until November 29, 2024, at 22:00.

Message

APRON MAIN RAMP WIP OPN EXCAVATION ADJ SE SIDE BARRICADED 2410291907-2411292200

Map Visualization

Preview
Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

10/019 NOTAMR 
Q) KZBW/QMNHW/IV/BO/A/000/999/4209N07242W005 
A) KBAF 
B) 2410291907 
C) 2411292200 

E) MAIN RAMP WIP OPN EXCAVATION ADJ SE SIDE BARRICADED