B2497/26
Checking status...
ADRunway Operations

Runway 12R/30L strip work is in progress between taxiways C6 and C9.

2026-10-05 23:00 - 2026-11-30 23:00
Duration:2 months

Period of Applicability

2026-10-05 23:00 - 2026-11-30 23:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Work is in progress on the runway strip for Runway 12R/30L between taxiways C6 and C9.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

B2497/26 NOTAMN
Q) MMFR/QMWHW/IV/M/A/000/999/2102N08653W002
A) MMUN
B) 2610052300
C) 2611302300
E) STRIPS RWY 12R/30L WIP BTN TWYS C6 AND C9