ADApron Operations

Phases 1 and 2 of AIP Supplement 08/26 are complete; phase 3 is active.

2026-11-05 09:38 - 2026-12-06 12:00
Duration:2 months

Period of Applicability

2026-11-05 09:38 - 2026-12-06 12:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

For AIP Supplement 08/26 dated 11 February 2026, phases 1 and 2 are complete and phase 3 is active.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A3832/26 NOTAMR A3509/26
Q) OEJD/QMPHW/IV/NBO/A/000/999/2141N03909E005
A) OEJN
B) 2611050938 C) 2612061200
E) REF AIP SUP 08/26 DATED 11 FEB 2026 PHASE 1 PHASE 2 CMPL AND
PHASE 3 ACT.