N3965/26
Checking status...
ADLighting Systems

Approach guidance lights for runways 08 and 26 are unserviceable.

2026-10-02 04:22 - 2027-01-01 09:00
Duration:LONG4 months

Period of Applicability

2026-10-02 04:22 - 2027-01-01 09:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Due to construction, approach guidance light 2 for runway 08 and approach guidance lights 2 and 5 for runway 26 are unserviceable.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

N3965/26 NOTAMR N2940/26
Q)RJJJ/QLJAS/IV/BO/A/000/999/3307N13947E005
A)RJTH B)2610020422 C)2701010900
E)FLW APCH-GUIDANCE-LGT U/S DUE TO CONST
APCH-GUIDANCE-LGT 2 FOR RWY 08
APCH-GUIDANCE-LGT (2),(5) FOR RWY 26