ADRunway Operations

Runway 01 threshold displaced due to work in progress.

2026-10-17 09:00 - 2026-11-17 21:00
Duration:aggregated 16 days

Period of Applicability

2026-10-17 09:00 - 2026-11-17 21:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Runway 01 threshold displaced 810 m due to work in progress; 2,693 m of runway is available. Personnel and equipment are in the area. Coordinate operations with AFIS on 118.8 MHz daily between 0900 and 2100.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A0655/26 NOTAMN Q) SGFA/QMTCM/IV/NBO/A/000/999/2203S06037W005 A) SGME B) 2610170900 C) 2611172100 D) DLY BTN 0900-2100 E) DTHR 01 810M DUE WIP RWY AVBL 2693M MEN AND EQPT IN THE AREA OPS COOR WITH AFIS FREQ 118,8MHZ