Period of Applicability
2026-08-01 04:00 - 2026-10-30 09:00
Timeline Visualization
Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.
7 days free trial, then $24.9/month. Cancel anytime.
Interpretation
Daily from 0400 to 0900, when RWY 11 is operational, THR 29 is displaced 1,200 m toward the ARP; when RWY 29 is operational, THR 11 is displaced 1,200 m toward the ARP. Displaced-threshold daytime markings are available. Work is in progress on the closed segment, with equipment up to 3 m high. In either configuration, the operational runway dimensions are 2,700 x 60 m; TORA and LDA are 2,700 m, while ASDA and TODA are 2,900 m. The 200 m concrete clearway may be used as a stopway. Available approaches are NDB Z, NDB Y, DVOR Z, DVOR Y and visual approaches for RWY 11; and DVOR Z, DVOR Y and visual approaches for RWY 29.