OTHOther

Installation of stormwater drainage near runway 11/29.

2024-09-04 07:00 - 2024-12-04 23:59
Duration:LONG4 months

Period of Applicability

2024-09-04 07:00 - 2024-12-04 23:59

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

At a distance of 270 meters from the axis of runway 11/29 between the apron and taxiway M, there is an installation of stormwater drainage involving construction equipment with a crane boom outreach of up to 25 meters.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A5923/24 NOTAMN
Q) UWWW/QMAHW/IV/B/A/000/999/5536N04917E005
A) UWKD B) 2409040700 C) 2412042359
E) AT DIST 270 M FROM AXIS OF RWY 11/29 BTN APN AND TWY M ALONG ENTIRE
LENGTH OF RWY INSTALLATION OF STORMWATER DRAINAGE CARRIED OUT WITH
INVOLVEMENT OF CONST EQPT WITH CRANE BOOM OUTREACH UP TO 25 M.