A2494/26
Checking status...
ADRunway Operations

AIP Supplement 27/25 is suspended; availability of runways 07L/25R, 07C/25C and 07R/25L changes during the flight check.

2026-11-07 18:00 - 2026-11-07 23:59
Duration:VERY SHORT6 hours

Period of Applicability

2026-11-07 18:00 - 2026-11-07 23:59

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Due to a flight check, AIP Supplement 27/25 is suspended. On November 7 from 1800 to 2059, the north runway (07L/25R) is closed on standby, the centre runway (07C/25C) is available, and the south runway (07R/25L) is closed for maintenance. From 2100 to 2259, the north and centre runways are available while the south runway remains closed for maintenance. From 2300 to 2359, all three runways are available.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A2494/26 NOTAMN
Q) VHHK/QMRAH/IV/BO /A /000/999/2219N11355E005
A) VHHH B) 2611071800 C) 2611072359
E) DUE FLTCK, AIP SUP 27/25 IS SUSPENDED. RWY AVBL AS FLW:
NOV 7 1800-2059
NORTH RWY (RWY 07L/25R) CLSD ON STANDBY
CENTRE RWY (RWY 07C/25C) AVBL
SOUTH RWY (RWY 07R/25L) CLSD FOR MAINT
NOV 7 2100-2259
NORTH RWY (RWY 07L/25R) AVBL
CENTRE RWY (RWY 07C/25C) AVBL
SOUTH RWY (RWY 07R/25L) CLSD FOR MAINT
NOV 7 2300-2359
NORTH RWY (RWY 07L/25R), CENTRE RWY (RWY 07C/25C) AND
SOUTH RWY (RWY 07R/25L) AVBL
Was this helpful?