A1701/26
Checking status...
ADLighting Systems

New PAPI installation is in progress for runway 09/27; existing PAPI systems remain primary and pilots should exercise caution.

2026-07-30 11:45 - 2026-09-04 18:30
Duration:2 months

Period of Applicability

2026-07-30 11:45 - 2026-09-04 18:30

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Installation of new four-lamp frangible PAPI systems with dual interleaved circuits is in progress for both directions of runway 09/27. Work is restricted to scheduled runway closures; the new PAPI systems will remain switched off during operations, while the existing PAPI systems remain available and primary. No simultaneous visual display or runway operational impact is expected, and pilots should exercise caution.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A1701/26 NOTAMN
Q) VIDF/QLPCS/IV/NBO/A /000/999/2646N08053E005
A) VILK B) 2607301145 C) 2609041830
E) RWY 09/27 - NEW PAPI INSTL WIP. EXISTING PAPI REMAINS AVBL AND
PRIMARY FOR OPS. INSTL OF NEW 4-LAMP FRANGIBLE PAPI WITH DUAL
(INTERLEAVED) CIRCUITS IN PROGRESS FOR BOTH RWY DIRECTIONS AT
361.017M FM THR RWY 27 AND 360.196M FM THR RWY09, 15M FM RWY EDGE.
ALL WORK RESTRICTED TO SKED RWY CLOSURES. NEW PAPI WILL REMAIN
SWITCHED OFF DRG OPS. ENSURING NO SIMULTANEOUS VISUAL DISPLAY AND NO
IMPACT ON RWY OPS. PILOTS TO EXER CTN.)