A2652/26
Checking status...
ADLighting Systems

New PAPI installation is in progress for RWY 09/27; the existing PAPI remains primary and the new PAPI is off during operations.

2026-11-04 06:19 - 2027-01-15 18:30
Duration:3 months

Period of Applicability

2026-11-04 06:19 - 2027-01-15 18:30

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Installation of new four-lamp frangible PAPI units with dual interleaved circuits is in progress for both directions of RWY 09/27. The units are positioned 361.017 m from the RWY 27 threshold and 360.196 m from the RWY 09 threshold, 15 m from the runway edge. Work is restricted to scheduled runway closures. The existing PAPI remains available and primary for operations; the new PAPI will remain switched off during operations to prevent simultaneous visual displays. No impact on runway operations is expected, but pilots should exercise caution.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A2652/26 NOTAMR A2008/26
Q) VIDF/QLPXX/IV/NBO/A/000/999/2646N08053E005
A) VILK B) 2611040619 C) 2701151830
E) RWY 09/27 - NEW PAPI INSTL WIP. EXISTING PAPI REMAINS AVBL AND
PRIMARY FOR OPS. INSTL OF NEW 4-LAMP FRANGIBLE PAPI WITH
DUAL(INTERLEAVED) CIRCUITS IN PROGRESS FOR BOTH RWY DIRECTIONS AT
361.017M FM THR RWY 27 AND 360.196M FM THR RWY09, 15M FM RWY EDGE.
ALL WORK RESTRICTED TO SKED RWY CLOSURES. NEW PAPI WILL REMAIN
SWITCHED OFF DRG OPS. ENSURING NO SIMULTANEOUS VISUAL DISPLAY AND NO
IMPACT ON RWY OPS.PILOTS TO EXER CTN.