A2425/26
Checking status...
ADApron Operations

Work in progress on areas near taxiway V and stands 52, 55A and 74.

2026-07-19 00:00 - 2026-08-19 16:59
Duration:2 months

Period of Applicability

2026-07-19 00:00 - 2026-08-19 16:59

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Work in progress on two areas near taxiway V and the taxi lanes into stands 52, 55A and 74, including an area adjacent to the VAECO fence.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A2425/26 NOTAMN
Q) VVHN/QMAHW/IV/BO/A/000/999/2113N10548E005
A) VVNB B) 2607190000 C) 2608191659
E) WIP ON AREAS, DETAILS AS FLW:
- AREA 1:
+ THE NORTHERN: 265M FM CL OF TWY V, 33.5M FM CL OF TXL
INTO STAND 52, 27M FM CL OF TXL INTO STAND 55A
+ THE WESTERN: 62M FM EXTENDED CL OF TXL W5
+ THE EASTERN: 33M FM EXTENDED CL OF TXL W7
- AREA 2:
+ THE NORTHERN: 248M FM CL OF TWY V, 54M FM THE SAFETY
LIMIT LINE AT STAND 74
+ THE WESTERN: ADJ TO VAECO FENCE.