A4143/26
Checking status...
ADLighting Systems

Runway 16 approach lighting is manually operated, with delayed intensity activation expected.

2026-10-20 07:00 - 2026-12-20 16:00
Duration:3 months

Period of Applicability

2026-10-20 07:00 - 2026-12-20 16:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

The approach lighting system for runway 16 is manually operated; expect a delay in activating its intensity.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A4143/26 NOTAMN
Q) WMFC/QLAXX/IV/NBO/A /000/999/0138N10340E005
A) WMKJ B) 2610200700 C) 2612201600
E) ALS RWY 16 MANUALLY OPERATED. DELAY IN INTENSITY ACTIVATION
EXPECTED