L1701/26
PERM
Checking status...
ADRunway Operations

Runway 03/21 pavement strength ratings have changed.

2026-10-24 18:00 - PERM
Duration:PERMANENT

Period of Applicability

2026-10-24 18:00 - PERM

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Runway 03/21 pavement strength ratings have changed: from the runway 03 threshold to 300 m, the concrete section has PCR 1210/R/A/W/T; from 300 m to 3,600 m, the asphalt section has PCR 840/R/A/W/T.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

L1701/26 NOTAMN
Q)ZLHW/QMBCH/IV/BO/A/000/999/3819N10624E005
A)ZLIC B)2610241800 C) PERM
E) RWY03/21 STRENGTH PCR CHANGED AS FLW:
1. 0M-300M FM RWY03 THR, PCR 1210/R/A/W/T, CONC.
2. 300M-3,600M FM RWY03 THR, PCR 840/R/A/W/T, ASPH.
Was this helpful?