Work is in progress in two areas north of the runway centerline and east of the runway 06 threshold.

2026-09-11 15:00 - 2026-10-31 23:00
Duration:aggregated 17 days EST

Period of Applicability

2026-09-11 15:00 - 2026-10-31 23:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Work in progress within two areas north of the runway centerline and east of the runway 06 threshold: 140–370 m north and 1,052–2,016 m east, and 370–500 m north and 945–2,016 m east. The work is scheduled daily from 1500 to 2300.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

Y1207/26 NOTAMN
Q)ZYSH/QFAHW/IV/NBO/A/000/999/4651N13028E005
A)ZYJM B)2609111500 C)2610312300 EST
D)1500-2300 DLY
E) WIP WI FLW AREA:
1. 140M-370M NORTH OF RCL, 1,052M-2,016M EAST OF RWY06 THR.
2. 370M-500M NORTH OF RCL, 945M-2,016M EAST OF RWY06 THR.