A2517/26
Checking status...
NavApproach Procedures

Runway 26L ILS and LOC approaches are suspended; RNP only, with LNAV not authorized during parallel operations.

2026-05-31 23:59 - 2026-08-31 23:59
Duration:LONG4 months

Period of Applicability

2026-05-31 23:59 - 2026-08-31 23:59

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Changes to approach procedures due to renewal of ILS runway 26L (IMSW). Runway 26L ILS and LOC approaches are temporarily suspended. RNP approach is available only. During parallel operations announced on ATIS, LNAV is not authorized; LNAV/VNAV or LPV are to be used only. If unable, inform ATC on initial contact.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A2517/26 NOTAMN
Q) EDMM/QPIAU/I /NBO/A /000/999/4821N01147E005
A) EDDM B) 2605312359 C) 2608312359
E) CHANGES TO APCH DUE TO RENEWAL OF ILS RWY 26L (IMSW):
RWY 26L: ILS AND LOC APCH TEMPO SUSPENDED.
RNP APPROACH AVAILABLE ONLY.
DURING PARALLEL OPERATIONS (ANOUNCED ON ATIS) LNAV NOT AUTHORIZED
LNAV/VNAV OR LPV TO BE USED ONLY. IF UNABLE INFORM ATC ON INITIAL
CONTACT.