A0825/26
Checking status...
ADRunway Operations

Runway 10/28 is closed for work, and arrivals and departures must not be planned during the closure.

2026-11-03 22:27 - 2026-11-07 05:00
Duration:VERY SHORTaggregated 16 hours

Period of Applicability

2026-11-03 22:27 - 2026-11-07 05:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Runway 10/28 is closed for work in progress as part of Phase 4 of AIP SUP 01/26, scheduled 0100–0500. Operators must not plan arrivals or departures during the closure. The closure start may be delayed until 0130 for delayed movements on request and subject to ATC approval; the runway will be available no later than 0500. Confirm actual closure times via ATIS or ATC.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A0825/26 NOTAMR A0815/26
Q) GMMM/QMRHW/IV/NBO/A/000/999/3137N00802W005
A) GMMX
B) 2611032227 C) 2611070500
D) 0100-0500
E) REF AIP SUP NR 01/26 WEF 27 APR 2026 PHASE 4 AND NOTAM A0776/26:
WIP AS COMPLEMENT TO PHASE 4 OF AIP SUP 01/26.
RWY 10/28 CLSD DUE WIP.
OPR SHALL NOT PLAN ARR OR DEP DURING CLOSURE.
START OF CLOSURE MAY BE DELAYED UP TO 0130 FOR DELAYED MOV, ON RQ
AND SUBJ ATC APPROVAL.
RWY AVBL NLT 0500.
ACTUAL CLOSURE TIMES CFM VIA ATIS AND ATC.
Was this helpful?