11/003
Checking status...
ADTaxiway Operations

Construction work adjacent to taxiway B between taxiways B4 and B5 is lighted and barricaded.

2026-11-02 14:01 - 2026-12-01 07:59
Duration:29 days

Period of Applicability

2026-11-02 14:01 - 2026-12-01 07:59

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Construction work is in progress adjacent to the west edge of taxiway B between taxiways B4 and B5; the work area is lighted and barricaded.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A1471/26 NOTAMN Q) KZSE/QMXHW////000/999/4731N12218W005 A) KBFI B) 2611021401 C) 2612010759 E) TWY B BTN TWY B4 AND TWY B5 WIP CONST ADJ WEST EDGE LGTD AND BARRICADED