ADTaxiway Operations

Taxiway P is commissioned between Taxiway A and Runway 09R/27L.

2026-08-07 21:21 - PERM
Duration:PERMANENT

Period of Applicability

2026-08-07 21:21 - PERM

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Taxiway P is commissioned between Taxiway A and Runway 09R/27L. It is 200 feet long by 90 feet wide, has an asphalt surface, is lighted, and has a pavement classification rating of PCR 825.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A0646/26 NOTAMN Q) KZJX/QMXXX////000/999/2806N08038W005 A) KMLB B) 2608072121 C) PERM E) TWY P COMMISSIONED BTN TWY A AND RWY 09R/27L 200FT X 90FT ASPH LGTD PCR825