Period of Applicability
2026-03-20 15:07 - 2026-06-18 10:00
Timeline Visualization
Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.
7 days free trial, then $24.9/month. Cancel anytime.
Interpretation
From 19 Feb to 31 Jul 2026, Roma/Ciampino Airport is conducting markings removal and replacement works to create three new stands; phases 1 and 2 are completed and phase 3 is active.