B2019/25
NOTAM Active
Construction Activity

Expansion works of airport terminal at Pisa/S.Giusto (LIRP)

2025-04-18 05:42 - 2025-07-09 23:59

Period of Applicability

2025-04-18 05:42 - 2025-07-09 23:59

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, cancel anytime

Interpretation

The expansion works of the airport terminal at Pisa/S.Giusto (LIRP) are currently ongoing, with phase 1 completed and phase 2 active. The works are scheduled to be in force from 05 September 2024 to 22 October 2025.

Message

SUP S28/24 IN FORCE FROM 05 SEP 2024 TO 22 OCT 2025 'PISA/S.GIUSTO (LIRP) AD: EXPANSION WORKS OF AIRPORT TERMINAL' STATUS OF WORKING PHASES: - PHASE 1: COMPLETED - PHASE 2: ACTIVE

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

B2019/25 NOTAMR B1319/25
Q) LIMM/QFAXX/IV/BO /A /000/999/4341N01024E005
A) LIRP B) 2504180542 C) 2507092359
E) SUP S28/24 IN FORCE FROM 05 SEP 2024 TO 22 OCT 2025
'PISA/S.GIUSTO (LIRP) AD: EXPANSION WORKS OF AIRPORT TERMINAL'
STATUS OF WORKING PHASES:
- PHASE 1: COMPLETED
- PHASE 2: ACTIVE
Issued at: 2025-04-18 05:43