A0508/26
Checking status...
OBSTemporary Obstacles

Two mobile cranes and two concrete pumps erected at Hoersching with obstacle marking.

2026-03-06 13:05 - 2026-06-03 13:00
Duration:3 months

Period of Applicability

2026-03-06 13:05 - 2026-06-03 13:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Two mobile cranes and two concrete pumps are erected at Hoersching at 48°13′59″N 014°09′52″E with a maximum height of 11 m (37 ft) AGL, elevation 310 m (1018 ft) AMSL; obstacles are marked by day and night.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A0508/26 NOTAMN
Q) LOVV/QOBCE/IV/M  /AE/000/011/4814N01410E001
A) LOWL B) 2603061305 C) 2606031300
E) 2 MOBILE CRANES AND 2 CONCRETE PUMPS ERECTED AT HOERSCHING
PSN: 481359N 0140952E
MAX HGT: 11M/37FT AGL
ELEV: 310M/1018FT AMSL
OBST DAY AND NIGHT MARKED
Was this helpful?