ADRunway Operations

Runway 12/30 has construction work in progress on the north side.

2026-05-26 13:00 - 2026-06-19 20:00
Duration:aggregated 8 days

Period of Applicability

2026-05-26 13:00 - 2026-06-19 20:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Runway 12/30 is work in progress for construction adjacent north side daily 1300-2000.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A0091/26 NOTAMN Q) TJZS/QMRHW////000/999/1800N06633W005 A) TJPS B) 2605261300 C) 2606192000 D) DLY 1300-2000 E) RWY 12/30 WIP CONST ADJ N SIDE