A1628/26
Checking status...
ADRunway Operations

Both runway 31 shoulders are excavated for rear hook assembly gear installation.

2026-07-22 07:25 - 2026-10-21 23:59
Duration:LONG4 months

Period of Applicability

2026-07-22 07:25 - 2026-10-21 23:59

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Work is in progress to install rear hook assembly gear for runway 31. Both runway shoulders are excavated between DTGM 2 and DTGM 1; the excavated area is 140 m by 12 m by 0.45 m and 2 m from the runway edge. Aircraft must exercise caution for personnel and materials.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A1628/26 NOTAMR A0979/26
Q) VIDF/QMWHW/IV/NBO/A/000/999/3359N07447E005
A) VISR B) 2607220725 C) 2610212359
E) WIP FOR INSTALLATION OF REAR HOOK ASSEMBLY GEAR FOR RWY 31. CTN
FOR BOTH RWY SHOULDERS DUG UP BTN DTGM (DISTANCE TO GO MARKER) 2 TO
DTGM 1 FOR RWY 31.
1) DIMENSION OF DUG UP AREA 140M X 12M X 0.45M. DIST FM RWY EDGE
2M. ALL ACFT EXER CTN FOR MEN AND MATERIAL.