Construction Activity

Construction work in progress near the main runway with a 5m high barrier installed.

2025-02-04 04:08 - 2025-05-05 23:59

Period of Applicability

2025-02-04 04:08 - 2025-05-05 23:59

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, cancel anytime

Interpretation

Work in progress for construction of parallel taxiway south of main runway 10/28. A foreign object debris barrier with a height of 5m is installed at a distance of 135m from the runway centerline.

Message

WIP FOR CONST OF PARL TWY SOUTH OF MAIN RWY 10/28.FOREIGN OBJECT DEBRIS BARRIER OF HGT 5M INSTL AT A DIST OF 135M FM RCL

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A0393/25 NOTAMR A3355/24
Q) VOMF/QMXHW/IV/BO/A/000/999/1743N08313E005
A) VOVZ B) 2502040408 C) 2505052359
E) WIP FOR CONST OF PARL TWY SOUTH OF
MAIN RWY 10/28.FOREIGN OBJECT DEBRIS BARRIER 
OF HGT 5M INSTL AT A DIST OF 135M FM RCL
Issued at: 2025-02-04 04:12