Runway Operations

Construction work on a new access road on the north side of runway 10/28.

2025-06-19 10:33 - 2025-07-31 18:59

Period of Applicability

2025-06-19 10:33 - 2025-07-31 18:59

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, cancel anytime

Interpretation

Construction work for a new access road is taking place on the north side of runway 10/28, approximately 25 meters from the runway centerline, extending 280 meters to the north. Work is scheduled from June 19, 1033 to 1859, and daily from July 1 to July 31, 0100 to 1859.

Message

CONST WORK OF A NEW ACCESS ROAD ON THE N SIDE OF RWY10/28. WORK WILL BE CARRIED OUT FM THE EDGE OF RWY APRX 25M AWAY FM THE RCL TO A DIST OF APRX 280M TO THE N WI THE AREA BOUNDED BY COORD 004124S0730...

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A0243/25 NOTAMR A0240/25
Q) VRMF/QMWHW/IV/M/A/000/999/0042S07309E005
A) VRMG
B) 2506191033 C) 2507311859
D) JUN 19 1033-1859 20-30 0100-1859, JUL 01-31 0100-1859
E) CONST WORK OF A NEW ACCESS ROAD ON THE N SIDE OF RWY10/28.
WORK WILL BE CARRIED OUT FM THE EDGE OF RWY APRX 25M AWAY FM THE
RCL TO A DIST OF APRX 280M TO THE N WI THE AREA BOUNDED BY COORD
004124S0730903E-
004132S0730902E-
004132S0730901E-
004124S0730902E-
004124S0730903E
WORK AREA WILL BE VACATED AND ALL EQPT WILL BE MOVED 75M AWAY FM
RCL 30 MIN PRIOR TO ALL FLIGHT MOV