A1009/25
Checking status...
Runway Operations

Runway 09/27 closed daily from 1800 to 2300 due to work in progress.

2025-04-12 18:00 - 2025-07-10 23:00

Period of Applicability

2025-04-12 18:00 - 2025-07-10 23:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, cancel anytime

Interpretation

Runway 09/27 is closed due to work in progress, with no exceptions. The closure is scheduled daily from 1800 to 2300.

Message

RWY 09/27 CLSD DUE TO WIP RMK: NO EXCEPTION

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A1009/25 NOTAMN
Q) WAAF/QMRLC/IV/NBO/A/000/999/0845S11510E005
A) WADD 
B) 2504121800 
C) 2507102300
D) DAILY 1800-2300
E) RWY 09/27 CLSD DUE TO WIP
RMK: NO EXCEPTION