A1549/26
Checking status...
ADRunway Operations

Runway 15/33 strip is work in progress with heavy equipment present.

2026-04-30 10:32 - 2026-07-15 17:00
Duration:3 months

Period of Applicability

2026-04-30 10:32 - 2026-07-15 17:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Strip runway 15/33 is work in progress at multiple positions beyond threshold runway 33, abeam threshold runway 15, and before threshold runway 15; heavy equipment is present and all traffic is subject to ATC clearance.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

A1549/26 NOTAMR A1480/26
Q)WIIF/QMWHW/IV/M/A/000/999/0047S10017E005
A)WIEE
B)2604301032
C)2607151700
E)STRIP RWY 15/33 WIP PSN AS FLW :
- 880M BEYOND THR RWY 33,30M NORTHEAST OF CENTERLINE
- 835M BEYOND THR RWY 33,47M NORTHEAST OF CENTERLINE ALONG 276M
- 372M BEYOND THR RWY 33,40M SOUTHWEST OF CENTERLINE ALONG 460M
- ABEAM THR RWY 15,83M NORTHEAST OF CENTERLINE ALONG 2221M
- 59M BEFORE THR RWY 15 ALONG 362M
RMK: - HEAVY EQPT PRESENT
- ALL TFC SUBJ ATC CLR