Period of Applicability
2026-04-15 09:21 - 2026-07-14 15:59
Timeline Visualization
Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.
7 days free trial, then $24.9/month. Cancel anytime.
Interpretation
Work in progress within multiple defined areas adjacent to RWY 15: (1) 906–1,320 m south of RWY 15 threshold and 80–157 m east of the runway centerline; (2) 1,100–1,243 m south of RWY 15 threshold and 157–171 m east of the runway centerline; (3) from 10 m north of RWY 15 threshold to 906 m south and 129–163 m east of the runway centerline; (4) 495–545 m south of RWY 15 threshold and 164–263 m east of the runway centerline.