ADTaxiway Operations

Taxiway A and B segments are closed due to work in progress.

2026-06-30 17:00 - 2026-09-29 23:00
Duration:aggregated 23 days

Period of Applicability

2026-06-30 17:00 - 2026-09-29 23:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, then $24.9/month. Cancel anytime.

Interpretation

Taxiway A between taxiway B2 and taxiway B4, taxiway A between taxiway B4 and taxiway B7, taxiway B between taxiway B2 and taxiway B4, and taxiway B between taxiway B5 and taxiway B7 are closed due to work in progress. Schedule: 1700-2300 daily.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

G2502/26 NOTAMN
Q)ZJSA/QMXLC/IV/M/A/000/999/1818N10925E005
A)ZJSY B)2606301700 C)2609292300
D)1700-2300 DLY
E) FLW TWY CLSD DUE TO WIP:
1.TWY A BTN TWY B2 AND TWY B4.
2.TWY A BTN TWY B4 AND TWY B7.
3.TWY B BTN TWY B2 AND TWY B4.
4.TWY B BTN TWY B5 AND TWY B7.