A0655/25
Checking status...
Taxiway Operations

Multiple taxiways (P3, P4, P5, C3 and fast exit C4) are closed due to upgrade work with personnel and equipment present.

2025-08-28 21:00 - 2025-11-26 05:00

Period of Applicability

2025-08-28 21:00 - 2025-11-26 05:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, cancel anytime

Interpretation

Phase 2 upgrade work on the parallel taxiway P is effective 16 January 2025; taxiways P3, P4, P5, C3 and fast exit C4 are closed. Work is scheduled nightly 2100-0500; presence of personnel and equipment in the area, caution recommended and follow ATC instructions.

Message

REF AIP SUP NR 01/25 WEF 16 JAN 2025 PHASE 2: DUE TO UPGRADE WORK ON PARALLEL TWY P SECTION P3, P4 AND STRIPS; TWY P3, P4, P5, C3 AND FAST EXIT C4 ARE CLSD. PRESENCE OF PERSONS AND EQPT. CAUTION RECOMMENDED. FOLLOW ATC INSTRUCTIONS.

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

Q) GMMM/QMXLC/IV/M/A/000/999/3137N00802W005
A) GMMX
B) 2508282100 C) 2511260500
D) 2100-0500
E) REF AIP SUP NR 01/25 WEF 16 JAN 2025 PHASE 2:
DUE TO UPGRADE WORK ON PARALLEL TWY P SECTION
P3, P4 AND STRIPS;
TWY P3, P4, P5, C3 AND FAST EXIT C4 ARE CLSD.
PRESENCE OF PERSONS AND EQPT.
CAUTION RECOMMENDED.
FOLLOW ATC INSTRUCTIONS.