Apron Operations

Construction work is in progress at the south cargo ramp apron affecting 350 feet northwest.

2025-02-26 12:56 - 2025-07-01 21:00

Period of Applicability

2025-02-26 12:56 - 2025-07-01 21:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, cancel anytime

Interpretation

The south cargo ramp apron is undergoing construction work, affecting an area of 350 feet northwest. The work is scheduled to take place from February 26, 2025, to July 1, 2025.

Message

APRON SOUTH CARGO RAMP NW 350FT WIP CONST 2502261256-2507012100

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

02/484 NOTAMR 
Q) KZOB/QMNHW/IV/BO/A/000/999/4124N08151W005 
A) KCLE 
B) 2502261256 
C) 2507012100 

E) SOUTH CARGO RAMP NW 350FT WIP CONST
Issued at: 2025-02-26 12:56