H2423/25
Checking status...
Runway Operations

RWY 07/25 closed due to work in progress.

2025-04-03 12:00 - 2025-04-03 19:00

Period of Applicability

2025-04-03 12:00 - 2025-04-03 19:00

Timeline Visualization

Get instant access to visual timeline analysis and NOTAM scheduling information with Notamify Pro.

7 days free trial, cancel anytime

Interpretation

Runway 07/25 is closed due to work in progress. Taxiing is available between Taxiway B and Taxiway D. Please refer to the method of working plan 24/001 for details.

Message

RWY 07/25 CLOSED DUE WIP TAXIING AVBL BTN TWY B AND TWY D REFER METHOD OF WORKING PLAN 24/001

Map Visualization

Loading map data
Please wait...
© OpenStreetMap contributors

Raw NOTAM

H2423/25 NOTAMN
Q) YMMM/QMRLC/IV/NBO/A/000/999/3357S15111E005
A) YSSY
B) 2504031200 C) 2504031900
E) RWY 07/25 CLOSED DUE WIP
TAXIING AVBL BTN TWY B AND TWY D
REFER METHOD OF WORKING PLAN 24/001
Issued at: 2025-03-27 03:37